I - HOW TO APPLY?
- Download and accomplish Energization Request for Meteringforms
- File the application and submit all necessary documents (refer to Section II below)
- Pay the required fees (see Section III below)
- Visit NGCP website or call for information and guidance
- Obtain the Metering Service Agreement
II - WHAT ARE THE REQUIREMENTS?
- Accomplished Form/s
- RE Service/Operating Contract from DOE-REMB
- System Impact Study
- Facilities Study
- Connection Agreement
- Transmission Service Agreement (TSA)
- Metering Installation Registration Form/s
- Single-line and Three-line Diagrams
- ERC Certification of Meter Test Results
- Test and Calibration Reports of Instrument Transformers and Meters
- Remote Terminal Unit (RTU) Installation
- Metering Facility
III - HOW MUCH TO PAY?
- Refer Customer Bulletins for the updates on Schedule of Rates/Fees
I - HOW TO APPLY?
- Download and accomplish application form
- File the application and submit all necessary documents (refer to Section II below)
- Pay the required fees (see Section III below)
- Visit NGCP website or call for information and guidance
- Obtain the Certificate
II - WHAT ARE THE REQUIREMENTS?
- System Impact Study
- Proposed single-line diagram of customer facilities
- Equipment specification
- System grounding
- Revenue metering equipment
-
Protective relays [ERC RESOLUTION NO. 18 ,Series of 2015]
-
Protection scheme (user specific);
- Single Circuit I Double Circuit;
- Conventional Generation;
- New Technology (Type ¾ Wind Power Plant / Solar PV Power Plant);
- Load Customers; and
- Setting Guidelines;
- Protection Single Line Diagram; and,
- Technical Specifications.
-
Telecom, NDME, SCADA2
- Specific technology applicable (user specific); FO/MW/PLC;
- Schematic/Connection Diagram; and,
- Technical Specifications (RTU, Communication Protocol, etc.)
- Implementation schedule
- Bill of quantities
- Project cost
- Transmission line / Substation design
- Other grid code requirements
III- HOW MUCH TO PAY?
- Refer Customer Bulletins for the updates on Schedule of Rates/Fees
I - HOW TO APPLY?
- Download and accomplish application form
- File the application and submit all necessary documents (refer to Section II below)
- Pay the required fees (see Section III below)
- Visit NGCP website or call for information and guidance
II - WHAT ARE THE REQUIREMENTS?
- RE Service/Operating Contract from DOE - REMB
- Clearance to undertake the System Impact Study (SIS) from DOE - EPIMB
- Letter of Intent from the Generator Customer
- Proposed plant details and specifications
- Target commissioning date
- Connection scheme to be agreed by both NGCP and Customer
- BIR and SEC registration
- Additional Requirements:
- NGCP to conduct the SIS
- Vicinity map of the Project
- Single Line Diagram of the proposed connection scheme/s indicating the parameters of the connection facilities such as line structure, conductor type and distance, and transformer capacities
- Generator modeling parameters
- Transmission Service Application Form (TSAF)
- Agreement on Offer of Service
- Third Party to conduct the SIS*
- Vicinity map of the Project
- Single Line Diagram of the proposed connection scheme/s indicating the parameters of the connection facilities such as line structure, conductor type and distance, and transformer capacities
- Generator modeling parameters
- Transmission Service Application Form (TSAF)
- Agreement on Offer of Service
- Tripartite Confidentiality Agreement
III - HOW MUCH TO PAY?
<49 MW = Php600,000
|
≥50 MW = Php1million
|
60% down and 40% before SIS delivery
|
*If SIS is conducted by a Third Party, NGCP charges Data fee and Review Fee.
Please see concerned officers for rates.
I - HOW TO APPLY?
- Download and accomplish Transmission Service application forms
- File the application and submit all necessary documents (refer to Section II below)
- Pay the required fees (see Section III below)
- Visit NGCP website or call for more information and guidance
- Obtain the Certificate
II - WHAT ARE THE REQUIREMENTS?
- Letterof Application for Transmission Service
- ERC Load Approval
- DOE Accreditation (Generator)
- System Impact Study
- Offer of Service for Facilities Study
- Connection Agreement
- Submission of Statement of Readiness to Connect
-
Issuance of Certificate of Technical Requirements
- District Office Clearance
- Metering Services Group (MSG) Clearance
- Maintenance and Testing Division (MTD) Clearance
- System Operator (SO) Clearance (if applicable)
- Serving of Transmission Service Agreement (TSA)
-
Relevant Schedules
- Open Access Transmission Service (OATS) Services
- Standard Planning Data
- Detailed Planning Data (for Generator Customers)
- Electrical Drawings
- Connection Point Drawings
- Asset Boundary
- Protection Arrangement and Settings
- Metering Requirements
- Notices
- Provisional Maintenance Schedule
- Testing and Commissioning (new delivery Point)
- Load Shedding
- Contingency Actions
- Critical Events List
- Statement of Readiness to Connect (new delivery Point)
- Issuance of Approval to Connect
- Energization of Customer’s Facilities
- Payment of Security Deposit
III - HOW MUCH TO PAY?
- Customer Bulletins for the updates on Schedule of Rates/Fees