I - HOW TO APPLY?

  1. Download and accomplish Energization Request for Meteringforms
  2. File the application and submit all necessary documents (refer to Section II below)
  3. Pay the required fees (see Section III below)
  4. Visit NGCP website or call for information and guidance
  5. Obtain the Metering Service Agreement

 

II - WHAT ARE THE REQUIREMENTS?

  1. Accomplished Form/s
  2. RE Service/Operating Contract from DOE-REMB
  3. System Impact Study
  4. Facilities Study
  5. Connection Agreement
  6. Transmission Service Agreement (TSA)
  7. Metering Installation Registration Form/s
  8. Single-line and Three-line Diagrams
  9. ERC Certification of Meter Test Results
  10. Test and Calibration Reports of Instrument Transformers and Meters
  11. Remote Terminal Unit (RTU) Installation
  12. Metering Facility

 

 

III - HOW MUCH TO PAY?

  1. Refer Customer Bulletins for the updates on Schedule of Rates/Fees

I - HOW TO APPLY?

  1. Download and accomplish application form
  2. File the application and submit all necessary documents (refer to Section II below)
  3. Pay the required fees (see Section III below)
  4. Visit NGCP website or call for information and guidance
  5. Obtain the Certificate

 

II - WHAT ARE THE REQUIREMENTS?

  1. System Impact Study
  2. Proposed single-line diagram of customer facilities
  3. Equipment specification
  4. System grounding
  5. Revenue metering equipment
  6. Protective relays [ERC RESOLUTION NO. 18 ,Series of 2015]
    1. Protection scheme (user specific);
      1. Single Circuit I Double Circuit;
      2. Conventional Generation;
  • New Technology (Type ¾ Wind Power Plant / Solar PV Power Plant);
  1. Load Customers; and
  2. Setting Guidelines;
  1. Protection Single Line Diagram; and,
  2. Technical Specifications.
  1. Telecom, NDME, SCADA2
    1. Specific technology applicable (user specific); FO/MW/PLC;
    2. Schematic/Connection Diagram; and,
    3. Technical Specifications (RTU, Communication Protocol, etc.)
  2. Implementation schedule
  3. Bill of quantities
  4. Project cost
  5. Transmission line / Substation design
  6. Other grid code requirements

 

III- HOW MUCH TO PAY?

  1. Refer Customer Bulletins for the updates on Schedule of Rates/Fees

 

 

I - HOW TO APPLY?

  1. Download and accomplish application form
  2. File the application and submit all necessary documents (refer to Section II below)
  3. Pay the required fees (see Section III below)
  4. Visit NGCP website or call for information and guidance

 

II - WHAT ARE THE REQUIREMENTS?

  1. RE Service/Operating Contract from DOE - REMB
  2. Clearance to undertake the System Impact Study (SIS) from DOE - EPIMB
  3. Letter of Intent from the Generator Customer
  4. Proposed plant details and specifications
  5. Target commissioning date
  6. Connection scheme to be agreed by both NGCP and Customer
  7. BIR and SEC registration
  8. Additional Requirements:
    1. NGCP to conduct the SIS
  1. Vicinity map of the Project
  2. Single Line Diagram of the proposed connection scheme/s indicating the parameters of the connection facilities such as line structure, conductor type and distance, and transformer capacities
  • Generator modeling parameters
  1. Transmission Service Application Form (TSAF)
  2. Agreement on Offer of Service

 

    1. Third Party to conduct the SIS*
  1. Vicinity map of the Project
  2. Single Line Diagram of the proposed connection scheme/s indicating the parameters of the connection facilities such as line structure, conductor type and distance, and transformer capacities
  • Generator modeling parameters
  1. Transmission Service Application Form (TSAF)
  2. Agreement on Offer of Service
  3. Tripartite Confidentiality Agreement

III -  HOW MUCH TO PAY?

<49 MW = Php600,000

≥50 MW = Php1million

60% down and 40% before SIS delivery

 

*If SIS is conducted by a Third Party, NGCP charges Data fee and Review Fee. 

Please see concerned officers for rates.

 

I - HOW TO APPLY?

  1. Download and accomplish Transmission Service application forms
  2. File the application and submit all necessary documents (refer to Section II below)
  3. Pay the required fees (see Section III below)
  4. Visit NGCP website or call for more information and guidance
  5. Obtain the Certificate

 

II - WHAT ARE THE REQUIREMENTS?

  1. Letterof Application for Transmission Service
  2. ERC Load Approval
  3. DOE Accreditation (Generator)
  4. System Impact Study
  5. Offer of Service for Facilities Study
  6. Connection Agreement
  7. Submission of Statement of Readiness to Connect
  8. Issuance of Certificate of Technical Requirements
    1. District Office Clearance
    2. Metering Services Group (MSG) Clearance
    3. Maintenance and Testing Division (MTD) Clearance
    4. System Operator (SO) Clearance (if applicable)
  9. Serving of Transmission Service Agreement (TSA)
  10. Relevant Schedules
    1. Open Access Transmission Service (OATS) Services
    2. Standard Planning Data
    3. Detailed Planning Data (for Generator Customers)
    4. Electrical Drawings
    5. Connection Point Drawings
    6. Asset Boundary
    7. Protection Arrangement and Settings
    8. Metering Requirements
    9. Notices
    10. Provisional Maintenance Schedule
    11. Testing and Commissioning (new delivery Point)
    12. Load Shedding
    13. Contingency Actions
    14. Critical Events List
    15. Statement of Readiness to Connect (new delivery Point)
  11. Issuance of Approval to Connect
  12. Energization of Customer’s Facilities
  13. Payment of Security Deposit

 

III - HOW MUCH TO PAY?

  1. Customer Bulletins for the updates on Schedule of Rates/Fees

 

 

©Copyright 2024 EVOSS. All rights reserved.